Direct Answer: A Victorian house-and-land loan settles in two stages: first the land settlement (once the lot titles), followed by 5 progress draws paid directly to your registered builder (base/slab, frame, lock-up, fixing and completion) under a fixed-price HIA or Master Builders contract. During construction, you typically pay interest only on funds drawn to date, keeping cash flow manageable while you rent.

Victorian Statutory Default Progress Payment Schedule (Full Build)

Under Victoria's Domestic Building Contracts Act 1995 (Consumer Affairs Victoria), unless both parties agree in writing to a compliant alternative schedule, standard full-build contracts of $20,000 or more follow a maximum 5% deposit plus five statutory progress stages totalling 100%:

Stage VIC Statutory Default % What the Bank Checks Before Paying
Deposit (pre-draw) Up to 5% Paid by borrower from deposit funds (contracts of $20,000 or more) once Domestic Building Insurance (DBI) and fixed-price contract are in place.
1. Base / Slab 10% Council building permit, DBI certificate, fixed-price contract, builder invoice & borrower sign-off.
2. Frame 15% Registered building surveyor frame inspection certificate + builder progress invoice.
3. Lock-Up 35% External walls, roof, windows and lockable doors complete; lender valuer progress inspection.
4. Fixing 25% Internal linings, cabinetry, tiling, plumbing and electrical fit-off complete.
5. Completion Remaining balance (10% when a 5% deposit is paid) Certificate of Occupancy, final bank valuation sign-off, and building insurance certificate of currency.

4 Pitfalls Along the Craigieburn–Mickleham–Wallan Corridor

Structuring Your Northern Corridor Build Across 50+ Lenders

Xcel Funding works daily with first home buyers and upgraders building across Craigieburn, Mickleham & Wallan, Wollert & Epping North, Sunbury, and Huntly & Epsom (Bendigo). Compare construction loan policies, valuation turnarounds and 5% Deposit Scheme eligibility on a free 15-minute phone call.

Frequently Asked Questions

Do I make full principal-and-interest repayments while my house is being built?

No. Most Australian construction loans default to interest-only repayments during the build (typically up to 12 months), charged only on the funds drawn so far — starting with the land loan and stepping up after each builder progress draw — before converting to principal and interest after completion.

When should I apply for a construction loan if my land in Mickleham or Wallan is untitled?

Run a borrowing-capacity and deposit check before signing the land contract, then lodge your formal land-and-construction application once you have your fixed-price building contract and confirmed title registration date (typically 60 to 90 days before land settlement).

Can I use the $10,000 Victorian FHOG and 5% Deposit Scheme on a house-and-land package?

Yes, if you meet eligibility rules and the combined land plus building contract stays at or below $750,000 for the Victorian FHOG (and at or below $950,000 in Greater Melbourne, Geelong and eligible corridor localities such as Wallan (3756), or $650,000 in rest-of-Victoria localities, for the Federal 5% Deposit Scheme).

Want a tailored Victorian lender comparison across 50+ banks?

Speak directly with Tanveer (CR 568072 under ACL 389087, AFG) — serving Northern Victoria and Melbourne's Northern Suburbs. General credit information only; formal recommendations follow a full assessment of your circumstances.